Reported events
17.11.17 - Ascó I y II (Tarragona) – INES 0 (Preliminar)
17.11.17 - Ascó I y II (Tarragona) – INES 0 (Preliminar).pdf
Version 1.3 Approved- Document Type
- Basic Document
- Extension
- Size
- 160 KB
- Modified
- 17/11/17, 16:39 by Natalia Muñoz
- Created
- 18/11/17, 02:30 by Natalia Muñoz
- Expiration Date
- Never Expire
- Review Date
- Never Review
- Location
- ASCÓ I
- Tags
- isn 24h
- Description
- El titular de la central nuclear Ascó ha comunicado al Consejo de Seguridad Nuclear (CSN), siguiendo el procedimiento establecido, que no se estaban realizando parte de las comprobaciones exigidas en un requisito de vigilancia de las Especificaciones Técnicas de Funcionamiento (ETF) relacionado con la instrumentación del sistema de actuación de las salvaguardias tecnológicas.
- Categories
- Sucesos Suceso 24 H Instalaciones nucleares Ascó 2017
Ocurrence Date
18/11/17, 01:30
Publish Date
18/11/17, 01:30
2017-11-17T14:31:14Z
nmm
2017-11-17T14:31:14Z
application/pdf
2017-11-17T14:31:14Z
nmm
2017-11-17T14:31:14Z
2017-11-17T14:31:14Z
-
Version 1.3By Natalia Muñoz, on 17/11/17, 16:39No Change Log
-
Version 1.2By Natalia Muñoz, on 17/11/17, 16:33No Change Log
-
Version 1.1By Natalia Muñoz, on 17/11/17, 16:32No Change Log
-
Version 1.0By Natalia Muñoz, on 17/11/17, 16:29No Change Log