Reported events
14.06.2018 - Ascó I (Tarragona) - INES 0
14.06.2018 - Ascó I (Tarragona) - INES 0.pdf
Version 1.0 Approved- Document Type
- Basic Document
- Extension
- Size
- 159 KB
- Modified
- 14/06/18, 15:41 by Arturo Fernández
- Created
- 14/06/18, 18:00 by Arturo Fernández
- Expiration Date
- Never Expire
- Review Date
- Never Review
- Location
- ASCÓ I
- Tags
- isn 24h asco i
- Description
-
El titular de la central nuclear de Ascó II (Tarragona) ha comunicado al Consejo de
Seguridad Nuclear (CSN), siguiendo el procedimiento reglamentario, que como
consecuencia de la revisión de las pruebas de conexión y desconexión de las cargas de los
generadores diésel, se ha detectado que no se comprobaba la desconexión de las bombas
del sistema de agua de refrigeración de servicios de salvaguardias ni de las bombas de
transferencia de gasoil, ya que estas bombas al realizarse la prueba están en situación de
reserva. - Categories
- Sucesos Suceso 24 H Instalaciones nucleares Ascó 2018
Ocurrence Date
13/06/18, 16:00
Publish Date
14/06/18, 16:00
2018-06-14T11:42:24Z
2018-06-14T11:28:45Z
application/pdf
2018-06-14T11:42:24Z
2018-06-14T11:28:45Z
2018-06-14T11:42:24Z
-
Version 1.0By Arturo Fernández, on 14/06/18, 15:41No Change Log